Floor screed: thickness, materials and how long it takes to dry
Screed is the layer nobody sees, yet the whole floor sits on it. If it is the wrong thickness, cracks or is still damp when the finish goes down, problems appear months later: swollen laminate, lifting wood, cracked tiles. This guide explains what thickness you need, how to work out the materials and, above all, how long to wait before the next step.
Calculator: Concrete and screedCubic metres, kilograms and bags for screed, levelling or a slab.What screed is and when you need it
A sand and cement screed is a mortar laid over the concrete slab or over insulation. It has three jobs: bring the floor to the right level, cover pipes and cables, and give a flat, stable base for the finish.
In renovations you usually need it in three cases: when old tiles come up together with their bed, when water or heating pipes in the floor are replaced, and when floors in different rooms must be brought to one level.
What thickness you need
- Bonded screed on the slab: usually 25–50 mm. Floating screed on insulation: at least 50–65 mm for sand and cement in homes.
- Over pipes: at least 25–40 mm above the highest point of the pipes, so the layer doesn’t crack right over them.
- Underfloor heating: follow the system manufacturer, typically at least 45 mm over the pipes.
- Thin levelling: for unevenness of a few millimetres you don’t need screed; use a self-levelling compound at 3–10 mm.
Work out the final level from the top down: start from the finished floor height, subtract the floor finish and adhesive or underlay, and what is left is the screed thickness.
Bagged or site-mixed
Bagged screed is sold in 25 kg bags (sometimes 20 or 40 kg) and only needs water. It has a consistent mix, tested quality and often additives that reduce shrinkage or speed up drying. Ideal for small and medium areas and where a mixer can’t reach.
Site-mixed screed is made from cement and sharp sand, typically 1:4 to 1:5. It is cheaper in materials, but quality depends on the sand, the mix and the water. Too much water makes it easier to spread but weaker and more likely to crack.
For large areas, contractors pump ready-mixed or liquid (anhydrite) screed, which goes down fast and evenly.
How much material
Start from the volume: area × thickness. For a 3.5 × 4 m room (14 m²) at 50 mm, the volume is 14 × 0.05 = 0.7 m³. Add about 5% for unevenness and losses and you get 0.74 m³.
Bagged screed data sheets give about 16–20 kg of dry product per square metre per centimetre of thickness, or roughly 1,600–2,000 kg per cubic metre. At 2,000 kg/m³, 0.74 m³ is about 1,470 kg, or 59 bags of 25 kg: nearly one and a half tonnes to carry and mix.
| Thickness | kg per m² | 25 kg bags per 10 m² |
|---|---|---|
| 30 mm | ~63 | 26 |
| 40 mm | ~84 | 34 |
| 50 mm | ~105 | 42 |
| 60 mm | ~126 | 51 |
At 2,000 kg/m³ and 5% loss. For a quick calculation with your own dimensions use the concrete and screed calculator.
Steps
- Prepare the base: remove dust, oil and loose material. For a bonded screed use a bonding agent; damp down or prime very absorbent bases.
- Edge strip: fix a compressible strip a few millimetres thick around all walls, so the screed can move without cracking.
- Screed rails: with a level or laser, set rails at the finished height every 1.5–2 m.
- Lay and rule off: spread the screed between the rails, compact it and rule it off with a straight edge.
- Finish: depending on the floor, float the surface by hand or with a power float. Laminate and vinyl need a very flat, smooth surface.
- Curing: the screed must not dry too fast. In heat or draughts cover it with polythene and keep windows shut for the first days.
How long it must dry
This is the most important part and where most mistakes happen. You can walk on screed after a day or two, but it isn’t dry. The water in it has to leave gradually, and that takes much longer, especially with thicker screeds.
Laminate and wood floor manufacturers give a rule of thumb for sand and cement screed:
| Thickness | Approximate drying time |
|---|---|
| up to 40 mm | about 1 week per 10 mm |
| 50 mm | about 6 weeks |
| 60 mm | about 8 weeks |
| over 60 mm | +4 weeks for each extra 10 mm |
The first centimetres dry relatively quickly, but each extra centimetre in thick screeds adds a disproportionate amount of time. An 80 mm screed can need more than three months before a wood floor goes down.
These times are only a guide and depend heavily on season, temperature and ventilation. That is why manufacturers ask you to measure the moisture before laying wood or laminate, using a hygrometer hood (relative humidity) or the carbide (CM) method. The test costs little compared with a floor that has to come up.
Tiles are less demanding: many adhesives accept screeds that are a few weeks old. Always check the adhesive data sheet.
Fast-drying options
When time is short, there are fast-drying screeds and admixtures that cut the wait dramatically. They cost more, but in a renovation where every week of delay means rent or a postponed move, they often pay off. «Fast» applies at the temperature and thickness given on the data sheet.
Screed and underfloor heating
With underfloor heating the screed becomes part of the system: it stores heat from the pipes and passes it to the floor. Additives that improve conductivity and flexibility and a thicker edge strip are used. Before the finish goes down, the system is commissioned with a gradual heat-up and cool-down cycle that drives out moisture and reveals any cracks. Follow the manufacturer’s procedure and keep a record.
When the depth is very large
Sometimes, after removing old floors with a thick bed or levelling big differences, the depth needed exceeds 80–100 mm. A screed that thick is heavy, needs a lot of material and months to dry. Instead, use a lightweight fill (concrete with expanded clay or polystyrene beads) for most of the depth and a normal 40–50 mm screed on top, which reduces both the load and the time.
Common problems
Cracks
Usually caused by drying too fast, too much water in the mix, too little thickness or a missing edge strip. Large areas, over about 30–40 m², also need movement joints.
Hollow spots
If tapping gives a hollow sound, a bonded screed didn’t stick to the base or has come away. This happens when the base was dirty, dusty or too dry. Repair these areas before the finish goes down.
Dusting surface
A surface that dusts has a weak top layer, usually from too much water or fast drying. Grind it and treat it with a consolidating primer.
Laying on damp screed
The most expensive mistake: rising moisture swells laminate at the joints, lifts wood and causes mould under vinyl. Measure, don’t guess.
Summary
- Thickness depends on what is underneath and what goes on top, usually 40–65 mm.
- Bagged screed uses about 16–20 kg/m² per cm: at 50 mm, about 4 bags of 25 kg per square metre.
- An edge strip, good compaction and protection from fast drying prevent cracks.
- Before laminate or wood: about 1 week per 10 mm up to 40 mm, much longer beyond. Always measure moisture.